Doherty Drive Safe Routes to School

Current Sidewalk
Imrpvement Diagram

DESCRIPTION: Improvements to crosswalk, sidewalk, pathway and bike lanes to increase pedestrian and bicycle safety on Doherty Drive in front of Redwood High School.

LOCATION: Doherty Drive between the Riviera Circle (west) and Lucky Drive in Larkspur

BENEFIT: The sidewalks in front of Redwood High School are narrower than the segment of Doherty Drive west of the school, and do not effectively accommodate the combination of pedestrian and bicycle traffic and ADA accessibility in the area, and the roadway’s bike lanes do not meet current standards. This project will provide wider pedestrian and bicycle access, make crosswalk improvements, and connect the Redwood Marsh multi-use trail with the Doherty Drive multi-use pathway west of Riviera Circle.

BUDGET & FUNDING: (fully funded) FY 2017/18—none. Total $377,500 - TAM SP2S, gas tax

SCHEDULE (tentative): Construction Summer 2017